Tai Kwun – Centre for Heritage and Arts (formerly Central Police Station),
10 Hollywood Road, Central, Hong Kong
The Project includes HVAC, P&D and Fire Services. It is a conservation of 16 buildings of historical or architectural significance and several open spaces on the approximately 3.37-acre site. To support the activities on the revitalized site, two new buildings will be built to provide additional floor space for contemporary art and exhibition areas and plant rooms, and will help to reduce interventions to the historic buildings.

It is aimed that the new buildings will carefully inject fresh elements within the fabric of the existing buildings, adding new functions and synergy to the unique historic character of the site.
Hong Kong Science Park, Phases 3a and 3b
Pak Shek Kok, Tai Po
MVAC installation consists of chilled units of solar absorption type and water cooled cooling towers, thermal energy storage panel with phase charge material, solar hot water collector, AHU c/w heat wheel and VRV indoor unit.

Electrical installation consists of 3200A LV switchboards, 6 numbers of standby/emergency generators with rating from 650kvA to 100kVA, busduct, active harmonic filter (AHF) and central lighting control.


Hong Kong Sports Institute
25 Yuen Wo Road, Shatin
The 3rd phase development covers the main building that houses Athlete Hostel catering for 370 athletes, Lecture Theatre with 400 seats, Meeting and Activity Rooms.


Hong Kong Science Park, Phase 2 (Area A2 - Laboratory Building)
Pak Shek Kok, Tai Po (TPTL No. 182)
MVAC installation consists of Secondary Chilled Water Pump, Secondary Heating Water Pump, Air Handling Unit c/w UV lamps, air purifier and steam humidifier, Primary Air Handling Unit c/w Heat wheel, VRV Indoor Unit, Bubble Tight Damper and Laboratory Exhaust Fans.

Electrical installation consists of 3200A LV switchboards, 3 numbers of Standby/ Emergency generators with rating from 500kVA to 1500kVA, Busduct, Central Battery System (CBS), UPS, Active Harmonic Filter (AHF), AV System, and Emergency Call Bell.


Hong Kong Science Park, Phase 2, Main Works (Area B)
Pak Shek Kok, Tai Po (TPTL No. 182)
HVAC installation consists of Secondary Chilled Water Pump, Secondary Heating Water Pump, Air Handling Unit c/w UV lamps, air purifier and steam humidifier, Primary Air Handling Unit c/w Heat wheel, VAV box and VRV Indoor Unit, Heat Exchanger, CRAC Unit, Water Scrubber and Jet Fans.

Electrical installation consists of 3200A LV switchboards, 6 numbers of Standby/ Emergency generators with rating from 500kVA to 1000kVA, Busduct, Central Battery System (CBS), UPS, Active Harmonic Filter (AHF), AV System, Intercom, BRI System, Induction Loop and Emergency Call Bell.

Fire Services consists of Automatic Sprinkler System, Fire Alarm System, Fire Detection System, Fire Hydrant/Hosereel System, Fire Alarm Control, Total Gas Flooding Installation (FM200) and Portable Fire Extinguishers Installation.


Hong Kong Science Park, Phase 2 (Area C)
Pak Shek Kok, Tai Po (TPTL No. 182)
MVAC installation consists of Secondary Chilled Water Pump, Secondary Heating Water Pump, Air Handling Unit c/w UV lamps, air purifier and steam humidifier, Primary Air Handling Unit c/w Heat wheel, VAV box and VRV Indoor Unit.

Electrical installation consists of 3200A LV switchboards, 4 numbers of Standby/ Emergency generators with rating from 500kVA to 750kVA, Central Battery System (CBS), UPS, Active Harmonic Filter (AHF), AV System, Walkie Talkie, Intercom, BRI System, Induction Loop and Emergency Call Bell.


Kong Kong Science Park, Phase 2 (Area A)
Pak Shek Kok, Tai Po (TPTL No. 182)
MVAC installation consists of Cooling Tower, Water Cooled Chiller (14,000 tonnage cooling capacity), Heat Pump, Primary Water Pump, Condensing Water Pump, Water Cool A/C Unit and VRV.

Electrical installation consists of 3200A LV switchboards, 4 numbers of Standby/ Emergency generators, Central Battery System (CBS), UPS, Active Harmonic Filter (AHF), Emergency Call Bell, Walkie Talkie and Intercom.

Fire Services consists of Automatic Sprinkler System, Fire Alarm System, Fire Detection System, Fire Hydrant/Hosereel System, Fire Alarm Control, Total Gas Flooding Installation (FM200), Portable Fire Extinguishers Installation and Linear Heat Detection System.


Australian International School
3A號 Norfolk Rd, Kowloon Tong
ACMV installation consists of one air cooled chiller with 150 tonnes for the Gymnasium Block and heat pump split type A/C unit for Academic Block.

Fire Services installation consists of wet sprinkler, fire hydrant and hosereel system, manual fire alarm, visual fire alarm and addressable automatic fire detection and alarm system, portable fire extinguishers, pre-action system to serve Library and FM 200 Gaseous Extinguishing Total Flooding System.