Cyberport Development – Contract C1
Cyberport Road, Pok Fu Lam
ACMV installation consists of sea water cooled centrifugal chiller plant totalled 8500 tonnes and screw type air cooled chiler plant totalled 250 tonnes.

Electrical installation consists of 3,200A LV switchboards, standby / emergency generators with rating from 750 kVA to 1,500 kVA, UPS public address, SMARTV / BRI and emergency call bell system.

Fire Services installation consists of complete wet sprinkler, fire hydrant and hosereel system, manual fire alarm, visual fire alarm and addressable automatic fire detection and alarm system, portable fire extinguishers and pre-action sprinkler system.

Plumbing and Drainage installation consists of potable water supply, cleansing water supply, grey water, soil and waste disposal and rain water disposal (underground and above ground).

An E&M Package that includes HVAC, BMS, Electrical, ELV, P&D, Fire Services and Data Center.